Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

A.
Operational transfer alliance plan
B.
Program milestone list
C.
Program transition agreement
D.
Program scope statement