What diagramming technique are you using as a part of the risk identification process?

[tagged]
You are the project manager of QSL project for your organization. You are working with your
project team and several key stakeholders to create a diagram that shows how various elements
of a system interrelate and the mechanism of causation within the system. What diagramming
technique are you using as a part of the risk identification process?

PrepAway - Latest Free Exam Questions & Answers

A.
Predecessor and successor diagramming

B.
System or process flowcharts

C.
Cause and effect diagrams

D.
Influence diagrams