PrepAway - Latest Free Exam Questions & Answers

What component of the change control system communicates the approval or denial of a proposed change request?

[tagged]
Thomas is a key stakeholder in your project. Thomas has requested several changes to the
project scope for the project you are managing. Upon review of the proposed changes, you have
discovered that these new requirements are laden with risks and you recommend to the change
control board that the changes be excluded from the project scope. The change control board

agrees with you. What component of the change control system communicates the approval or
denial of a proposed change request?

PrepAway - Latest Free Exam Questions & Answers

A.
Configuration management system

B.
Scope change control system

C.
Integrated change control

D.
Change log


Leave a Reply