Frank is a project team member in your project. Frank has been adding changes to the software
interface for the software that your project is creating. Because Frank has been adding these
features new risks have entered into the project. You elect that these additions should be removed
from the project even if it takes extra time and money to remove the features. What are these
riskladen features called?

A.
Gold plating
B.
Scope creep
C.
Negative risks
D.
Corrective actions