Holly is the project manager of the NHQ project for her company. Her project sponsor, Tracy, has
requested that Thomas, the department manager, from the Risk Management Department, will
work with Holly to determine the effectiveness of the risk responses. Tracy and Thomas are
concerned that some of the risks within Holly’s project may not be addressed to depth they would
like. In this scenario, who is responsible for ensuring that risk audits are performed at an
appropriate frequency throughout the project?

A.
Thomas
B.
Tracy
C.
The project team
D.
Holly