You are the project manager of the HJH project for your company. In your project, you have
created the probability-impact risk matrix as shown in the following figure:
If Risk D happens in this project, how much will be left in the contingency reserve?

A.
$440,000
B.
$233,500
C.
$258,500
D.
$243,500