Nancy is the project manager of a project with 78 stakeholders. This is a high-profile project and
she needs to express to her project team and to the management the importance of
communication in this project. She would like to show the number of stakeholder communication
channels in the project. Based on this information how many communication channels exist within
this project?

A.
156
B.
3,003
C.
78
D.
6,084