You are the project manager of the GHY Project for your company. You need to complete a
project management process that will be on the lookout for new risks, changing risks, and risks
that are now outdated. Which project management process is responsible for these actions?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Risk planning
B.
Risk identification
C.
Risk monitoring and controlling
D.
Risk analysis