what type of risk response?

Gary has identified a project risk that could injure project team members. He does not want to
accept any risk where someone could become injured on this project so he hires a professional
vendor to complete this portion of the project work. This workaround to the risk event is known as
what type of risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Acceptance

B.
Transference

C.
Mitigation

D.
Avoidance