[tagged] Who is responsible for the stakeholder expectations management in a high-profile, high-risk project?

[tagged]
Who is responsible for the stakeholder expectations management in a high-profile, high-risk
project?

PrepAway - Latest Free Exam Questions & Answers

A.
Project risk assessment officer

B.
Project management office

C.
Project sponsor

D.
Project manager