You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can
depict the resources that will be used within the project. Which of the following diagrams will you
create to accomplish the task?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Roles and responsibility matrix
B.
Work breakdown structure
C.
Resource breakdown structure
D.
RACI chart