Terri is the program manager for her organization and she’s working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Add the change to the program scope herself, as she is a project manager
B.
Add the change request to the scope and complete integrated change control
C.
Document the change request in a change request form.
D.
Create a change request charter justifying the change request