PrepAway - Latest Free Exam Questions & Answers

You need to update the tasks in PW

PrepAway - Latest Free Exam Questions & Answers

Your organization uses Project Server 2013. You are the project manager of a schedule.
Team Members send you emails with their percentage complete on their assignments.
Your organization only uses the following two percentages for tracking tasks:
• 50% for tasks that are started
• 100% for tasks that are completed
You have Project Web App (PWA) and use the information from the emails to update the tasks.
You need to update the tasks in PWA.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)

A.
In PWA, open the Tasks screen, select the task(s), and enter 50% or 100% in the % Complete field.

B.
In PWA, open Project Center. Edit the Project, and enter either 50% or 100% in the % Complete
field of each task, as needed.

C.
In PWA, open Project Center. Edit the Project, select the task(s), and select the 50% or 100%
button in the ribbon.

D.
In PWA, open the Microsoft SharePoint site for the schedule, select the task(s), and update the %
Complete field to either 50% or 100%.

Explanation:


Leave a Reply