PrepAway - Latest Free Exam Questions & Answers

You need to include all projects and resolve the overallocations in the most cost-effective way

An organization is performing a Portfolio Analysis with Project Server 2013 to determine the projects
that will be executed the next year. The company has the following base staff: one application
developer, one business analyst, one project administrator, and one trainer.
The Resource Analysis is shown the following exhibit. (Click the Exhibit button.)

You need to include all projects and resolve the overallocations in the most cost-effective way.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Hire an additional business analyst.

B.
Revise the primary cost constraint.

C.
Enter new start dates.

D.
Use the Force In/Out feature.


Leave a Reply