You are a project manager for an organization that uses Project Server 2013. You and other project
managers use Project Professional 2013 to manage projects.
The resources on your project are overallocated due to work assigned across the enterprise. As a
result, some work on your project does not finish as scheduled. Some tasks are left partially
complete. Other tasks did not start at all.
You need to resolve this issue.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Select all tasks that are partially complete or did not start as scheduled and move incomplete
parts to status date.

B.
Move all tasks that are partially complete back one week.

C.
Move only the tasks that did not start forward by one week.

D.
Select all tasks that are partially complete or did not start as scheduled, and move completed
parts to status date.