You are a portfolio manager in an organization that uses Project Server 2013.
You plan to review the milestones status of a project named Proj1.
You need to create a graphical view of all milestones of Proj1 that allows you to see the Start and
Finish dates of each milestone. You need to accomplish this goal in the least amount of time.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Open Microsoft Visio and make a data connection against the Project Server database. Write a
query that returns the Name, Start, and Finish dates of all milestones of Proj1. Create a chart with
that information.

B.
Open Microsoft Excel and make a data connection against the Project Server database. Write a
query that returns the Name, Start, and Finish dates of all milestones of Proj1. Create a chart with
that information.

C.
Create a Project view named Milestones with the Task Name, Start, and Finish fields. Filter the
view by the Milestone field so that the view only shows milestone tasks. Open Proj1 in Project Web
App (PWA), choose the Milestones view, and select all the milestones. Then add them to the
Timeline.

D.
Create a Microsoft SQL Server Reporting Services (SSRS) report with a data connection against the
Project Server database. Write a query that returns the Name, Start, and Finish dates of all
milestones of Proj1. Create a chart with that information.