You are a program manager in the Project Management Office (PMO) of an organization that has
Project Server 2013.
You plan to have a weekly project meeting review with all the project managers, and one of the
topics that you will cover is the status of all active Issues.
Your need to create a report that displays the following information:
• Name, Status, Priority, and Resolution of all Issues
• Name, Owner, and Start and Finish date of all projects
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a Microsoft Excel Services report that pulls information from the Issues cube.

B.
Create a Microsoft Excel Services report that pulls information from the Microsoft SharePoint
Configuration Database.

C.
Create a Microsoft Excel Services report that pulls information from the Microsoft SharePoint
Content Database.

D.
Create a Microsoft Excel Services report that pulls information from the Project Server 2013
database.