PrepAway - Latest Free Exam Questions & Answers

Which three steps should you perform?

You are a project manager for an organization that uses Project Server 2013.
As part of a regular project review, you notice that several tasks of one of your projects that should
be finished are outdated.
You need to update those tasks with the exact percent complete as of today.
Which three steps should you perform? (Each correct answer presents part of the solution. Choose
three.)

PrepAway - Latest Free Exam Questions & Answers

A.
Open the project for editing in Project Web App (PWA).

B.
Type today’s date in the Actual Start field for each outdated task.

C.
Open the project for editing in Project Professional 2013.

D.
Type today’s date in the field Update work as complete through.

E.
click the Update Project button.


Leave a Reply