Which of the following rules pertaining to a Business Continuity Plan/Disaster Recovery Plan is incorrect?

Which of the following rules pertaining to a Business Continuity Plan/Disaster Recovery Plan is
incorrect?

PrepAway - Latest Free Exam Questions & Answers

A.
In order to facilitate recover, a single plan should cover all locations.

B.
There should be requirements for to form a committee to decide a course of action. These
decisions should be made ahead of time and incorporated into the plan.

C.
In its procedures and tasks, the plan should refer to functions, not specific individuals.

D.
Critical vendors should be contacted ahead of time to validate equipment can be obtained in a
timely manner.

Explanation:
This is not the best practice, even more for the CISSP exam. Continuity / recovery plans should be
make for every location in separate. This is because when there is a disaster, Its not usually in all the
different locations, its better to have one plan for each of it so you can use and follow only the plan
of the affected site and don’t bother the other ones.