What is the ideal approach for an Agile project manager to take when considering fractional
assignments?
A.
Do nothing, as fractional assignments will not impact project performance.
B.
Allow resources to be assigned to no more than two projects at a time.
C.
Only allow nonessential resources to be fractionally assigned.
D.
Avoid them and have resources assigned to only one project at a time.
D.
Avoid them and have resources assigned to only one project at a time.
0
0
multitasking creates WIP and in agile WIP is Work in play producing no value till completed
0
0