PrepAway - Latest Free Exam Questions & Answers

The team should:

A project team estimates that they should complete 30 story points in the current iteration.
Partway through the iteration they realize that they will complete 50 story points at their
current rate. The team should:

PrepAway - Latest Free Exam Questions & Answers

A.
Shorten the iteration to meet the estimated velocity.

B.
Continue to work with the estimated velocity.

C.
Increase their estimated velocity.

D.
Release members to meet the estimated velocity.

One Comment on “The team should:


Leave a Reply