PrepAway - Latest Free Exam Questions & Answers

Project managers use velocity to determine:

Project managers use velocity to determine:

PrepAway - Latest Free Exam Questions & Answers

A.
If the team is committing to an appropriate amount of work for the iteration.

B.
How much work each team member is capable of completing during an iteration.

C.
How much work teams that are similar in size are capable of completing during an
iteration.

D.
If the Product Owner is prioritizing work appropriately in preparation for iteration planning.

One Comment on “Project managers use velocity to determine:


Leave a Reply