In Agile risk management, a risk burndown chart is best used to:

In Agile risk management, a risk burndown chart is best used to:

PrepAway - Latest Free Exam Questions & Answers

A.
Qualitatively analyze the probability of a risk occurring.

B.
Track progress on risk reduction of technical risks.

C.
Document the external risks that could impact the project.

D.
Illustrate the project risk profile and new and changing risks.

2 Comments on “In Agile risk management, a risk burndown chart is best used to:

  1. mohsinalish5@gmail.com says:

    A risk burn down chart is a tool that project managers can use to show graphically how risk could affect project completion. It is designed to show risks that could be detrimental to the project as well as risks that could improve the project’s completion.
    B seems to be a better fit but D also competes well!!
    But I guess D stands on top as the risk can add up till the product is not completed. Hence new and changing risk needs to be added when and where need be.