You need to view graphically which tasks and resources are causing the $5,000.00 cost variance

You manage a project schedule by using Project Professional 2013. You are concerned about project
costs. After viewing the Cost Variance column, you realize that the project has a cost variance of
55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost
variance. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
View the Resource Graph’s Cumulative Cost view.

B.
View the Task Cost Overview report.

C.
View the Over Budget Tasks report.

D.
View the Cost Overrun report.