PrepAway - Latest Free Exam Questions & Answers

You need to access the report view that your company previously created…

You are a project manager who uses Project Professional 2013. You work in a software development
project, which is in progress and has reached 60% of actual progress. Your company decides to use
the new Project Reports views to communicate all the project progress across the key users. They
also decide to report information about a specific period only, normally one month behind the
current day. You need to access the report view that your company previously created; however,
you must only modify the period displayed in the report and ensure that another period will not be
presented. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Access your report and change the scale by zooming in and out.

B.
Access your report and create a new Date Range group.

C.
Access your report and use the default Date Range filter.

D.
Access your report view and edit the time category under the field list pane.

Explanation:


Leave a Reply