You need to implement a solution to meet the stakeholder’s request

You manage a project by using Project Professional 2013. A critical task is out of scope for the
project. The stakeholders suggest that the task be removed from the project but kept in the plan in
case the task is needed in the future. You need to implement a solution to meet the stakeholder’s
request. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Click on the task, and click Inactivate.

B.
Move the task to after the ending date for the project.

C.
Delete the task from the schedule.

D.
Click the Unlink Task button to unlink the predecessors and successors for the task.