You need to ensure that the effort for each resource and task is set up properly in the calendar

You are a project manager for a company that is based in New York and London. The company uses
Project Professional 2013. Teams from both offices are working together on a project. Since the two
offices are located in different regions, the teams have separate company holiday schedules and
working times. You need to ensure that the effort for each resource and task is set up properly in the
calendar. You want to achieve this goal by using the least amount of time and effort. What should
you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a London calendar from the standard calendar and assign the London calendar as the
project calendar.

B.
Create a new base calendar for London that includes all of the London office’s company holidays
and assign it to all London resources.

C.
Manually edit each London resource’s calendar to add all of the London office’s company holidays.

D.
Assign the 24-hour calendar to all tasks and select Scheduling ignores resource calendars.