You need to let the resource know how the Work will be affected

Your company uses Project Professional 2013. You are setting up a preliminary schedule by using
manually scheduled tasks. You create a task with no duration, start, or finish date, and then you
assign a resource. Later, you enter a duration of three days for that task. You need to let the
resource know how the Work will be affected. What should you say?

PrepAway - Latest Free Exam Questions & Answers

A.
Work will increase to 24 hours.

B.
Work will remain at 0 hours.

C.
Work will increase to 16 hours.

D.
Work will remain at 8 hours.