You send a sales quotation to a customer named Contoso, Ltd.
You have another customer named Lit ware, Inc.
Lit ware has a trade agreement in place, which includes two of the items in the sales quotation that was sent to Contoso.
You plan to copy the sales quotation to create a sales quotation for Lit ware.
You need to ensure that the sales quotation for Lit ware adheres to the trade agreement you have with Lit ware.
Which option should you select in the copy quotation function?

PrepAway - Latest Free Exam Questions & Answers

A.
Copy precisely

B.
Recalculate price

C.
Copy charges

D.
Delete quotation lines

Explanation:
Copy project quotations [AX 2012]
Use the following procedure to copy all or part of a project quotation.
1. Click Project management and accounting > Common > Quotations > Project quotations.
2. Select or open a project quotation.
3. On the Action Pane, on the Project quotation tab or Quotation tab, in the Copy group, click From all.

4. Under Setup, at the top of the Copy from all form, select one or more of the following options:
Select the Copy precisely check box to copy all dimensions, sales tax, and ledger o
accounts to the new project quotation. Delivery dates are not copied. Select the Delete quotation lines check box to delete any project quotation lines in the o
new project quotation before you copy project quotation lines from this form. Select the Copy quotation header check box to copy information from the selected o
project quotation to the new project quotation.