What should you configure?

You need to ensure that when users perform bill of materials (BOM) calculations, they receive a warning message if any manufactured components are missing an
active BOM.
What should you configure?

PrepAway - Latest Free Exam Questions & Answers

A.
A costing sheet

B.
Calculation groups

C.
Configuration groups

D.
Cost groups

Explanation:
Override group setup
Select whether you want to override the warning conditions that are associated with the BOM calculation group that is assigned to each item. The BOM calculation
generates an Infolog that contains warning messages that reflect applicable warning conditions.