What do these variance values mean?

You are a manager for an organization that uses Project Professional 2013. A critical project shows
average finish variance values between 5-10 days for the tasks. You need to interpret these variance
values to determine the next course of action to take. What do these variance values mean?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is on schedule.

B.
The project is running between 5-10 days ahead of schedule.

C.
The project is running between 5-10 days behind schedule.

D.
The project is averaging a normal performance timeline.