You need to update the actual work and mark the task complete

You are a project manager who uses Project Standard 2013. You manage a large project and are
capturing actual work for the tasks as they are being worked. You do not need to enter the time on
the actual day worked; however, you need to capture the total amount of time spent on the task.
The fixed work task has a baseline of 20 hours, and the developer’s timecard displays the following
hours:
Monday = 2 hours
Tuesday = 8 hours
Wednesday = 4 hours
Thursday = 2 hours
Friday = 2 hours
The developer informs you that the task is now complete.
You need to update the actual work and mark the task complete.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Open the Task Form and format it to show Work Details. Enter 20 hours in the Actual Work for the
resource. Enter 0 hours in the remaining work. Mark the task as 100% complete.

B.
Open the Task Form and format it to show Schedule Details. Enter 18 hours in the Actual Work for
the resource. Enter 2 hours in the remaining work. Mark the task as 100% complete.

C.
Open the Task Form and format it to show Work Details. Enter 18 hours in the Actual Work for the
resource. Enter 0 hours in the remaining work.

D.
Open the Task Form and format it to show Schedule View. Enter 18 hours in the Work column for
the resource.