you need to see all assignments with details for BA1 to understand their current workload before making any as

You are managing a project using Project Professional 2013. Your project schedule is showing task
overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to
investigate more details regarding the over allocations. You discover that the BA1 resource is
overallocated and you need to see all assignments with details for BA1 to understand their current
workload before making any assignment changes. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Click the BA1 resource and scroll to the end of the project.

B.
Click View, check Details, select Resource Form then click on the BA1 resource.

C.
Click View, check Details, select Task Form then click on the BA1 resource.

D.
Right-click the BA1 resource and select Information.