Which view should you use?

You are a project manager who uses Project Professional 2013. After updating a project schedule,
you want to determine the amount of time that the schedule has slipped from the original scheduled
dates. You need a graphical view that shows the current schedule to baseline. Which view should
you use?

PrepAway - Latest Free Exam Questions & Answers

A.
Detail Gantt view

B.
Tracking Gantt view

C.
Leveling Gantt view

D.
Gantt Chart view