PrepAway - Latest Free Exam Questions & Answers

You need to resolve the issue

You are managing a project by using Project Professional 2013, and you notice a potential scheduling
problem indicated by wavy red lines under some of the dates in the Finish column. You need to
resolve the issue. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Recalculate the project schedule.

B.
Adjust the resource assignment on the task to when the resource is available.

C.
Activate Task Inspector for the task to decide if adjustments are necessary.

D.
Adjust the finish date on the task to a date in the future.