PrepAway - Latest Free Exam Questions & Answers

You need to achieve this goal using a custom field

You are using Project Standard 2013. You want the ability to see only tasks that have finish dates
past their deadline date You need to achieve this goal using a custom field. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a Lookup containing the values Yes and No against the Task Text1 custom field. Write a
formula that compares the deadline date to the finish date and displays the correct value from the
Lookup table.

B.
Use the Task Flagl5 custom field. Write a formula that compares the deadline date to the finish
date, and set the result to Yes or No.

C.
Use the Task Text30 custom field, also known as the Deadline Flag, since it automatically provides
this capability.

D.
Rename the Task Number1 custom field to Deadline passed. Write a formula that compares the
deadline date to the finish date and displays Yes or No in the field.


Leave a Reply