PrepAway - Latest Free Exam Questions & Answers

which one?

You are the project manager of the NGQQ Project for your company. To help you communicate
project status to your stakeholders, you are going to create a stakeholder register. All of the
following information should be included in the stakeholder register except for which one?

PrepAway - Latest Free Exam Questions & Answers

A.
Identification information for each stakeholder

B.
Assessment information of the stakeholders’ major requirements, expectations, and potential
influence

C.
Stakeholder classification of their role in the project

D.
Stakeholder management strategy

Explanation:
The stakeholder management strategy is generally not included in the stakeholder registry because
it may contain sensitive information that should not be shared with project team members or
certain other individuals that could see the stakeholder register.
The stakeholder register is a project management document that contains a list of the stakeholders
associated with the project. It assesses how they are involved in the project and identifies what role
they play in the organization. The information in this document can be very perceptive and is meant
for limited exchange only. It also contains relevant information about the stakeholders, such as their
requirements, expectations, and influence on the project.
Answer option A is incorrect. Stakeholder identification should be included in the stakeholder
register.
Answer option B is incorrect. Assessment information should be included in the stakeholder register.
Answer option C is incorrect. Stakeholder classification should be included in the stakeholder
register.
“Project Management Body of Knowledge (PMBOK Guide), Fourth Edition”


Leave a Reply