What portion of the change control process oversees features and functions of the product scope?

You are documenting your organization’s change control procedures for project management. What
portion of the change control process oversees features and functions of the product scope?

PrepAway - Latest Free Exam Questions & Answers

A.
Configuration management

B.
Product scope management is outside the concerns of the project.

C.
Scope change control system

D.
Project integration management

Explanation:
Configuration management is responsible for documenting and controlling changes to the project’s
product.
Answer option B is incorrect. This is not a valid statement about the project’s product.
Answer option C is incorrect. The scope change control system focuses on changes to the project’s
scope, not directly to the product scope.
Answer option D is incorrect. Project integration management is a process that requires the project
manager and team to check the changes to all knowledge areas of the project.