Risk acceptance is a component of which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Assessment

B.
Mitigation

C.
Evaluation

D.
Monitoring

Explanation:

Risk acceptance is one of the alternatives to be considered in the risk mitigation process.
Assessment and evaluation are components of the risk analysis process. Risk acceptance is not a
component of monitoring.