A risk mitigation report would include recommendations for:

A risk mitigation report would include recommendations for:

PrepAway - Latest Free Exam Questions & Answers

A.
assessment.

B.
acceptance

C.
evaluation.

D.
quantification.

Explanation:

Acceptance of a risk is an alternative to be considered in the risk mitigation process. Assessment.
evaluation and risk quantification are components of the risk analysis process that are completed
prior to determining risk mitigation solutions.