PrepAway - Latest Free Exam Questions & Answers

Category: PR2P

Exam PR2P: PRINCE2 Practitioner

What will be the impact on the benefits?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
What will be the impact on the benefits?

What additional risk will this place on the project?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
What additional risk will this place on the project?

What products will be impacted by this change?

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
What products will be impacted by this change?

\\Nhat is the next action the Project Manager should co…

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of
the Outsourcing project, the proposed option exceeds tolerance. \\Nhat is the next action the Project Manager
should consider?

which statement about appointing the MFH Quality Manage…

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the
configuration management procedure is correct?

which statement about the Configuration Management Stra…

Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document
control process to manage all documentation requirements. The document control process was
created by the MFH Quality Manager, who now maintains all of MFH’s documents and performs an
organization-wide configuration management role. The MFH Quality Manager will administer the
configuration management procedure for the Restructuring project since this must comply with the
MFH document control process.
According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing
project is correct?

Hot Area:

HOTSPOT
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team
Manager after taking some time to understand the requirements of the project. A contract for their services has
been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This
contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish aschedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have
occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has
received no communication from the photographer. The Project Manager has tried to call the photographer and
has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and
prioritizing other clients’ work. If Portraits ltd do not deliver on schedule the project will be delayed and the
expected benefits will be reduced. The contract is to be reviewed and Portraits Ltd reminded of their
agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also
producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early
release of a competitor’s calendar may weaken the impact of the MNO Manufacturing Company calendar,
thereby reducing the anticipated benefits of the Calendar project.
There is a major concern over an apparent lack of control of project documentation.
For each concern listed in Column 1, select from Column 2 the configuration management task that could help
address the problem. Each selection from Column 2 can be used once, more than once or not at all.
Hot Area: