PrepAway - Latest Free Exam Questions & Answers

which of the following parties must be in attendance?

When a meeting is planned to obtain design approval for a legacy system interface, a representative
of which of the following parties must be in attendance?

PrepAway - Latest Free Exam Questions & Answers

A.
End-users

B.
Project Manager

C.
Project sponsor

D.
Information systems


Leave a Reply