All of the following are inputs to project schedule development EXCEPT:All of the following are inputs to proj

All of the following are inputs to project schedule development EXCEPT:All of the following are
inputs to project schedule development EXCEPT:

PrepAway - Latest Free Exam Questions & Answers

A.
change requests

B.
lead- and lag-times.

C.
resource requirements.

D.
resource availability.