what type of source selection process?

You are the project manager of the NHQ Project and are trying to determine which seller you
should choose for the project. You have received proposals from six vendors and they are all very
good proposal, qualified to complete the project work, and the prices are close to the same. You
would like to create method of ranking each vendor based and assign a score value to several
different categories. Because the project is a high-profile project, you have assigned 25 points to
experience and 10 points for all of the other categories to judge the vendors. This is considered
what type of source selection process?

Which of the following techniques of the activity process is Frank using in this example?

Frank is the project manager in BlueWell Inc. He is working with his project to subdivide the
project work packages into smaller, more manageable components. He and the project team are
planning in detail all of the things the team will need to create, purchase, or do in order to satisfy
the project scope. Management is concerned with the activity which Frank is using in this scenario,
as they believe that Frank is taking too long to complete this pre-execution activity. Which of the
following techniques of the activity process is Frank using in this example?

What scheduling technique is Kelly using?

Kelly is the project manager of her organization. She is reviewing the project network diagram to
confirm that the resource she has identified is available to complete the project assignments
without conflicting with other activities in the project node. The availability of resources will help
Kelly determine the final finish date for the project. What scheduling technique is Kelly using?

Which one of the following is the best example of a project constraint that will likely affect the projectR

Mary is the project manager for her organization. She is working with the project team to define
the project activities. She is concerned about some of the dependencies of the project work, which
may affect the project schedule. Which one of the following is the best example of a project
constraint that will likely affect the project’s ability to finish by a given deadline?

What does Anna want to create in this instance?

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of
which are external to her organization. In this project, Anna wants to create a method to classify
the stakeholders based on their level of authority and their level of concern regarding the project
outcomes. This model will help Anna determine the communication demands and when
information should be distributed. What does Anna want to create in this instance?