What is this schedule compression technique called?

Frank is the project manager of a construction project. In this project, Frank has elected to allow
the interior design phase of the project to overlap with the pool construction phase of the project.
Normally, Frank would not allow these two phases to overlap, but for this project, he has elected to
do so in order to compress the project schedule. What is this schedule compression technique
called?

What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?

Ned is the project manager of the HYQ Project. In Ned’s project, the management has requested
that he enforce resource leveling so that the maximum amount of hours in the project per worker
will not exceed 25 hours per week. Ned’s pay is based on how quickly he can complete the project
work. What must Ned do to accommodate the change in the resource allotment if he has to finish
the project on time?