You need to view only the tasks that currently affect the overall completion date

You have a project schedule in progress. You need to view only the tasks that currently
affect the overall completion date. What should you do in the Gantt Chart view?

PrepAway - Latest Free Exam Questions & Answers

A.
Apply the Priority group.

B.
Apply the Incomplete Tasks filter.

C.
Apply the Late Tasks filter.

D.
Apply the Critical Tasks filter.

E.
Apply the Status group.