PrepAway - Latest Free Exam Questions & Answers

What would you do first?

You need to create a new project schedule by using tasks from an existing project. You need
to achieve this goal without inheriting actual hours from the existing project. What would you
do first?

PrepAway - Latest Free Exam Questions & Answers

A.
On the File menu in Project 2010, use one of the existing templates.

B.
Save the task list in Microsoft Excel and use the Project Import Wizard.

C.
Open the previously saved project schedule and save it as a template.

D.
Save the task list as a Microsoft Excel template.


Leave a Reply