You need to replace the resource assignment for an in-progress task. You also need to
retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should
you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Use the Resource Name column drop-down list.

B.
Use the Resource Pool feature.

C.
Use the Team Planner feature.

D.
Use the Level Selected feature.