PrepAway - Latest Free Exam Questions & Answers

you need to display the following information: • Tasks that are not started

In the default Gantt Chart view of your Project Professional 2010 project, you need to display
the following information:
• Tasks that are not started.
• Tasks in progress.
• Tasks that have finished.
• Total remaining effort for each group of tasks.
What should you do on the View tab?

PrepAway - Latest Free Exam Questions & Answers

A.
Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field
to the table.

B.
Select Group by Complete and Incomplete Tasks, and then add the Work field to the
table.

C.
Select Group by Active v. Inactive, and then add the Remaining Work field to the table.

D.
Select Group by Active v. Inactive, and then add the Work field to the table.


Leave a Reply