PrepAway - Latest Free Exam Questions & Answers

You need to turn off the feature that triggers the dependency to be automatically added

Every time you create a new task within your project schedule, Project 2010 automatically
adds a dependency to the new task. You need to turn off the feature that triggers the
dependency to be automatically added. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
On the Advanced tab of the Project 2010 options, clear the Move selection after enter
check box.

B.
On the Schedule tab of the Project 2010 options, clear the Autolink inserted or moved
tasks check box.

C.
On the Advanced tab of the Project 2010 options, select the Ask to update automatic links
check box.

D.
Highlight all tasks and select Respect Links.


Leave a Reply